Feedback : Eastern Region > Sironko District > Nabweya > Zesui > Nabweya primary school > Sector [Education]

Feedback reference no: L-YYN-EHF
Responsible Institution Sector Subcounty/ Parish Location/ Facility Plan Status
Zesui Education Zesui - Nabweya Nabweya primary school Shs 50.7 million was allocated for3 classrooms constructed at Nabweya P/S at Nabweya primary school in the year from July 2013 to June 2014 Shs 94.4 million was spent between July 2013 and December 2013 on 3 classrooms constructed at Nabweya P/S at Nabweya primary school and the work is complete
Responsible Institution Sector Subcounty/ Parish Location/ Facility Budget Expenditure % Budget Spent Source of Funding
Q1 Q2 Q3 Q4 Total
Zesui Education Zesui - Nabweya Nabweya primary school 50.7 0.0 43.7 7.0 0.0 50.7 100% Conditional Grant to SFG
Post a Comment/Give feedback

General feedback

Leave this empty:

Detailed Feedback

  1. 1

    What is the quality of construction?





  2. 2

    What is the name of the contractor?

  3. 3

    In your opinion, does the amount spent represent good value for money?



  4. 4

    Upload Photo/Image of the facility under construction/being constructed.


Received Comments

From Feedback Posted on Offensive?
Anonymous
  • That was good observation by the councilor
  • Reply


1 Reply

Budget for that period provided for a 2 classroom 50.7 million and awarded at shs 48,700,000, 3classroom was an error in typing. ( From : Anonymous )

2015-06-26 13:53:29 Reported as offensive
  • The councilor reported that only 2 classrooms were constructed at Nabweya p/s yet the budget shows 3 classrooms.
  • Reply

2014-09-02 09:54:39 Reported as offensive