Feedback : Eastern Region > Busia District > > Busitema > > Sector [Works and Transport]

Feedback reference no: L-YYQ-SJD
Responsible Institution Sector Subcounty/ Parish Location/ Facility Plan Status
Busitema Works and Transport Busitema - Not Specified Not Specified Shs 4.5 million were allocated by Busitema for Maintenance of Community Access Roads July 2015 and June 2016 Shs 0.0 million were spent by Busitema for Maintenance of Community Access Roads July 2015 and June 2016
Responsible Institution Sector Subcounty/ Parish Location/ Facility Budget Expenditure % Budget Spent Source of Funding
Q1 Q2 Q3 Q4 Total
Busitema Works and Transport Busitema - Not Specified 4.5 0.0 0.0 0.0 0.0 0 0% Other Transfers from Central Government
Post a Comment/Give feedback

General feedback

Leave this empty:

Detailed Feedback

  1. 1

    What is the quality of the works?





  2. 2

    What is the name of the contractor?

  3. 3

    In your opinion, does the amount spent represent good value for money?



  4. 4

    Upload Photo/Image of the road works.


Received Comments

From Feedback Posted on Offensive?
Anonymous
  • works commenced mid Dec 2015 and no payments were effected by end of Dec. 2015
  • Reply

2016-02-23 06:47:00 Reported as offensive